Change Seeding Equipment, Row Spacing, or Product
Inspect and update the following items, if seeding equipment,
row spacing, or product is changed. (See METER SETUP AND OPERATION
section for detailed procedures.)
-
Remove or install meter covers and meter seals to match quantity
and position of primary air runs.
-
Cap off unused primary tubes.
-
Move tank pressurization hoses to active primaries.
-
Remove or install meter rollers to match quantity and position
of primary air runs.
-
Remove or install fine-tuning rings on meter rollers to match
number of secondary header ports.
-
Install or engage agitators above active primary air runs. Disengage
agitators above inactive primary air runs.
-
Change meter rollers to match product and application rates.
-
Program monitor with current information.
|
|
LD45720,0000536-19-20111114
|
|