Route Chute Cables

  1. LV23150
    LV23150-UN-23SEP14

    A - Tab

    B - Screw

    Move chute so tab (A) on chute is in line with edge of screw (B). Chute opening is towards the left-hand side.



  2. LVP11374
    LVP11374-UN-09APR21

    Right Cable Hidden for Clarity

    LVP11376
    LVP11376-UN-09APR21

    A - Washer

    B - Top Left Pulley

    C - Top Center Pulley

    D - Bottom Left Pulley

    E - Tab

    F - Cap Screw

    Route left (long) cable:

    1. Behind washer (A).

    2. Around the top left pulley (B).

    3. Around the top center pulley (C).

    4. Around the bottom left pulley (D).

    5. Around chute.

    6. Under tab (E).



  3. Use locking pliers to pull cable tight.

  4. Tighten cap screw (F).

  5. LVP11375
    LVP11375-UN-09APR21

    Left Cable Hidden for Clarity

    LVP11377
    LVP11377-UN-09APR21

    A - Washer

    B - Top Right Pulley

    C - Bottom Center Pulley

    D - Bottom Right Pulley

    E - Tab

    F - Cap Screw

    Route right (short) cable:

    1. Behind washer (A).

    2. Around the top right pulley (B).

    3. Around the bottom center pulley (C).

    4. Around the bottom right pulley (D).

    5. In front of chute.

    6. Under tab (E).



  6. Use locking pliers to pull cable tight.

  7. Tighten cap screw (F).

  8. Move the chute back to the original position.

AL61114,000070C-19-20210412