Adjusting Rolling Basket Down-Pressure and Transport Clearance

If less aggressive rolling basket action is desired, or if greater transport clearance is needed, relocate spring end connections to appropriate hole for desired down pressure.

AG,OUO1011,2701 -19-29MAR00-1/2


1. Loosen spring end hardware (A) but do not remove at this time.

2. Using depth control hydraulics, lower baskets to ground until spring end hardware is loose (no tension).

3. Remove cap screws and activate depth control hydraulics until spring end connections align with desired mounting hole (A-D).

4. Install hardware at holes and tighten to specification.

Specification

Hardware -Torque 109 N·m (80 lb-ft)

N47734


A-Hardware-Heaviest Down-Force
B-Mounting Hole-Heavy Down-Force
C-Mounting Hole-Medium Down-Force
D-Mounting Hole-Light Down-Force

AG,OUO1011,2701 -19-29MAR00-2/2