Bleeding Hydraulic Cylinders

causym CAUTION: Escaping fluid under pressure can penetrate skin causing serious injury to you or others. Avoid hazard by relieving pressure before disconnecting hydraulic or other lines. Tighten all connections before applying pressure. Search for leaks with a piece of cardboard. Protect hands and body from high pressure fluids.

If an accident occurs, see a doctor immediately. Any fluid injected into skin must be surgically removed within a few hours or gangrene can result. Doctors unfamiliar with this type of injury can call Deere & Company Medical Department in Moline, Illinois, or other knowledgeable medical source.

causym CAUTION: To avoid injury or death to you or others, stand clear of machine when wings are being bled. Mechanical or hydraulic failure can allow wings to fall rapidly.

causym CAUTION: Be certain cylinder and attaching hoses are fully charged with oil before bleeding system. Failure to do so will allow wings to fall rapidly when attempting to lower from folded position.

1. Verify tractor is full of hydraulic oil.

X9811
N39547

OUO6061,0001DB4 -19-17MAY05-1/9


NOTE: Front end of turnbuckles MUST be removed and turnbuckles laid down before starting bleed procedure.

2. Loosen cap screws (A-B) on fore-aft link plates.


A-Cap Screws
B-Cap Screws

N69482

OUO6061,0001DB4 -19-17MAY05-2/9


3. Remove front turnbuckle (A) hardware and retain. Move turnbuckle away from fore-aft plates.

N69332

Front Turnbuckle on Main Frame

N69481

Front Turnbuckle on Wings

OUO6061,0001DB4 -19-17MAY05-3/9


NOTE: Left-hand main frame cylinder does not have eyebolt nut. Secure cylinder in upright position using chain or wire.

4. Secure cylinder (A) in upright position by leaning cylinders against eyebolt nut (B) and retaining cylinder using wire or chain.

5. Repeat process for all depth control cylinders.

IMPORTANT: Follow bleed procedure EXACTLY as shown. Once cylinders are bled, turnbuckles MUST be installed BEFORE completing bleed procedure.

IMPORTANT: If performing bleed procedure on machines running different than 1800 rpm, bleed rate times MUST be adjusted to a 113 Lpm (30 gpm) per minute rate. Example: If tractor is running at 57 Lpm (15 gpm), then double all bleed times.

6. Follow specific bleed procedure.

7. Run tractor to 1800 rpm.

8. Extend cylinder rods fully for 3 minutes.

9. Retract cylinder rods fully for 30 seconds.

10. Extend cylinder rods fully for 2 minutes.

11. Retract cylinder rod fully for 30 seconds.

12. Extend cylinder rods fully for 2 minutes.


A-Cylinder
B-Nut

N69327
N69726

OUO6061,0001DB4 -19-17MAY05-4/9


NOTE: Support cylinder with wood block to ease installing to wheel module.

13. Attach left-hand side main frame cylinder rod (A) by extending rod just behind anchor casting (B).

14. Lift wheel module (C) with hoist to position anchor casting with cylinder rod and retain with pin.

15. Repeat process on other side.


A-Cylinder Rod
B-Anchor Casting
C-Wheel Module

N69328

OUO6061,0001DB4 -19-17MAY05-5/9


IMPORTANT: DO NOT ADJUST eyebolt end (D) too far back or interference with wing-fold cylinder (E) will occur causing machine damage.

16. Attach remaining cylinder rods by loosening nuts (A) on eyebolts. Move eyebolts to align cylinder rod with anchor casting (B) and retain with pin (C).


A-Nuts
B-Anchor Casting
C-Pin
D-Eyebolt End
E-Wing-fold Cylinder

N69329
N69711

OUO6061,0001DB4 -19-17MAY05-6/9


IMPORTANT: Turnbuckles MUST be installed to complete bleed procedure.

17. Install front turnbuckle (A) using existing hardware on main frame and wings.


A-Front Turnbuckle

N69332

Front Turnbuckle on Main Frame

N69481

Front Turnbuckle on Wings

OUO6061,0001DB4 -19-17MAY05-7/9


18. Tighten cap screws on fore-aft link plates to specification.

Specification

(A) 7/8 x 6 in. Cap Screws -Torque 617 N·m (455 lb-ft)

Specification

(B) 5/8 x 5-1/2 in. Cap Screws -Torque 230 N·m (170 lb-ft)


A-Cap Screws
B-Cap Screws

N69482

OUO6061,0001DB4 -19-17MAY05-8/9


IMPORTANT: Finish bleed procedure COMPLETELY to ensure all air is purged from system.

19. Finish bleed procedure by raising machine and keep in continuous flow for 2 minutes.

N69727

OUO6061,0001DB4 -19-17MAY05-9/9