Leveling Disk Gangs-5-Section
IMPORTANT:
To level machine correctly, it MUST BE LEVELED IN THE PROPER SEQUENCE as shown.
If leveling machine is not done in this sequence, machine will not be level and will not function correctly.
IMPORTANT:
Check tires for correct inflation before leveling.
Perform following procedure on a level surface.
Rephase depth control cylinders before leveling.
1.
Raise machine until standards are 51 mm (2 in.) above ground.
Push SCV III forward to extend hydraulic cylinders and fully lower gangs.
|