Remove broken belt.
-
Before cutting damaged areas or laces from belt, identify and
mark pulley side of belt. The pulley side of the belt has the most
contact with the rollers and no contact with the module. The pulley
side is identified by the shape of rivet head (A) on the lacing. The
lace rivet on the pulley side of the belt has a circular split in
it. The lace rivet head (B) on the side of the belt that contacts
the module has a circular dimple in it.
-

E40026-UN-30MAY96

E21798-UN-24JUN99
Remove damaged area using a square and a sharp knife. Check
to be sure that belt end was cut squarely.
-
NOTE: If belts are shorter than the specified dimensions, a
short piece of belt can be added. Splices (on same belt) must be at
least 305 mm (12 in.) apart.
Check belt length. Make sure that belt is neither longer nor
shorter than specified.
|
7760 RMB Belt Lengths
|
| |
Minimum
|
Repair
|
Maximum
|
|
Narrow Belts
|
18 057 mm (710-7/8 in.)
|
18 082 mm (711-7/8 in.)
|
18 107 mm (712-7/8 in.)
|
|
Wide Belts
|
18 210 mm (717 in.)
|
18 235 mm (718 in.)
|
18 260 mm (719 in.)
|
-
IMPORTANT: Trailing end of belt must be trimmed using dimensions
shown in illustration. DO NOT vary from these dimensions.
NOTE: Arrow shown in illustration indicates direction of belt
travel.

N88351-UN-12APR10
A - Dimension, 6 mm (0.25 in.)
B - Dimension, 19 mm (0.75 in.)
Trim trailing end of belt as shown.
-

E40773-UN-08AUG96
A - Lacing Tool
B - Holes
Position belt lacing tool (A) in vise with holes (B) toward
operator and shoulder of tool resting on jaws of vise.
-
IMPORTANT: Use only 17 lace segments on wide belts and 14 segments
on narrow belts. Using more or less segments can result in premature
lace failure.

E40774-UN-08AUG96
A - Rivet Pins
B - Lacing Tool
C - Lacing Strip
D - Stop Pins
Install lacing strip (C) in lacing tool (B). Make sure that
two rivet pins (A) on each lacing segment are inserted into each of
the 17 holes in tool for the wide belt or 14 of the 17 holes for the
narrow belt. Lacing segments must rest against stop pins (D).
-
Tighten vise until lacing strip is lightly gripped and belt
can be easily inserted.
-
IMPORTANT: When belts are connected, edges must be aligned to
prevent belt damage.
NOTE: Arrows shown in illustrations indicate direction of belt
travel as it corresponds to square and tapered ends of belt.

N88312-UN-12APR10
Wide Belt Lacing Offsets

N88311-UN-12APR10
Narrow Belt Lacing Offsets
A - Belt Edge (Leading End)
B - Belt Edge (Trailing End)
C - Dimension, 16 mm
D - Dimension, 19 mm
E - Dimension, 11 mm
F - Dimension, 14 mm
Laces use the same number of segments on each end of belt.
To keep belt edges aligned when belt is connected, laces must be offset
slightly as shown. The belt expands when laces are installed. Mark
offsets and adjust position of belt in lacing tool as necessary.
-

E40775-UN-08AUG96

E40776-UN-08AUG96
A - Stop Plate
B - Belt
C - Hand Punch
D - Pneumatic Hammer
Install belt (B) in lacing strip with pulley side of belt
toward operator. While holding edge of belt against stop plate (A),
uniformly push belt down to the stop pins. Make sure that lacing strip
is against stop pins.
-
Make sure that belt and lacing are positioned squarely in lacing
tool. Close vise on belt and lacing until distance between lacing
tool jaws equals width of belt.
-
IMPORTANT: If using a hand punch, using too large of a hammer
or striking punch too hard can damage lacing tool or belt lacing.
If using pneumatic hammer, too high air pressure and/or too
long riveting time can damage lacing tool or belt lacing.
Drive rivets through belt using a punch (C) or pneumatic hammer
(D).
Rivet the two outer lacing segments first, then working from
the outside to the inside, rivet remaining lacing segments.
-
If using punch (C), drive rivets until shoulder on punch shaft
contacts lacing tool jaw. Hit punch an additional time to ensure contact
between shoulder and jaw.
-
If using pneumatic hammer (D), set air pressure to 500—600
kPa (5—6 bar) (72—87 psi). Operate hammer for 1—2
seconds for each rivet. Re-riveting is usually not necessary.
-
Remove belt from vise and inspect lacing. All rivets must be
driven through belt and show punch marks in center of rivets.
-
IMPORTANT: Do not hit loop area of fastener when using hammer
to flatten heads of rivets.
Do not hit rivets too hard
or rivets can buckle and damage joints.

E40027-UN-30MAY96
Flatten Rivets
Put belt and lacing on a solid base. Flatten heads of rivets
using the flat face of a small hammer. Strike several rivets at a
time using a light tapping motion. Rivets must be flush with splice.
-
Repeat procedure for other end of belt.
-
IMPORTANT: Belt must be installed so that square cornered end
leads as belt moves in normal direction of travel.
Install belt in module builder. (See BELT ROUTING AND ROLL DIAGRAM
in this section.) Square cornered end of belt must lead the end with
trimmed corners as belt moves in normal direction of travel.
-
Connect belt ends and check alignment of belt edges approximately
51 mm (2 in.) back from end of belt.