Recording a Straight Path or Navigating Around Obstacles

PC9284-UN-29JUL06

PC9285-UN-08AUG06
A - Recording PAUSED
B - Bridge segment is generated to connect two points
C - Tractor path not recorded while paused
D - Recording UNPAUSED
E - Path recorded as a straight line between points
A and D
-
Start Recording
-
Select Pause Recording to temporary stop recording of a vehicle’s
path.
-
Select Recording to resume recording the Adaptive curve.
The distance between where recording was PAUSED and RESUMED
will be connected with a straight line. This can be helpful when there
is a long straight section of path or when navigating around obstacles.
The longest bridge segment (line segment created between
PAUSED and UNPAUSED) that can be created is a distance of 0.8 km (0.5
miles) (2,640ft). For a greater distance, the line segment will not
connect resulting in a gap in the path.
|
|
OUO6050,00010BC-19-20090412
|
|