Energize System

PC22535-UN-20APR16
A - Override Height Switch Checkbox
B - Start Button
Turn master switch off or leave diagnostics page to immediately
force valves to return to closed position and stop flow.
Use Energize System procedure to test for flow at openers, purge
air and vapor from NH3 delivery system, and fill cooler and hoses
with liquid anhydrous. Select Start button to fully open control valve
and section valves for a few seconds, and then automatically close
them.
-
Ensure that area is clear of people, pets, and livestock.
-
Position machine into the wind.
-
Turn master switch on.
-
Select Override Height Switch checkbox (A).
-
Select Start button (B). Valves stay open for a few seconds.
-
Repeat as needed.
|
|
RW00482,000067E-19-20171213
|
|