Backfill

  1. W01147
    W01147-UN-12AUG93

    When backfilling from a large pile, shovel off the top of the pile, pushing toward the excavation. Drag some soil back to form a work ramp of convenient grade.



  2. Approach the pile with a level bucket. Determine the amount of material to be pushed from the pile by actuating the lift and bucket controls.

OUO6064,000150B-19-20160506