Normally, a bank or stockpile is excavated from the bottom and then up the side. Work the face of the bank or stockpile evenly to prevent outcroppings and overhangs.
Work bank or stockpile with machine at a 90° angle to the bank or stockpile.
1.
Position bucket on the ground in return-to-dig position.
2.
Place gear shift lever in first or second gear depending on ground conditions.
In loose material, use second gear for better traction. Use first gear for better bucket fill.
3.
Move forward into the bank or stockpile.
NOTE:
Use differential lock as necessary.
4.
Raise and curl bucket as bucket fills.
|