Backfilling W01147-UN-12AUG93 When backfilling from a large pile, shovel off the top of the pile, pushing toward the excavation. Drag some soil back to form a work ramp of convenient grade.
Approach the pile with a level bucket. Actuate the lift and bucket controls to determine the amount of material to be pushed.