Recommended Set Up/Assembly Sequence

  1. Prepare the tractor.

    1. Refer to Preparing the Tractor section.

    2. Install mounting frames.

    3. Install toolbox support bracket and toolbox.

    4. Install hood guard.

    5. Install mid-mount couplers and hoses.

    6. Install hydraulic valves and controls as needed.

  2. Prepare the loader.

    1. Remove shipping banding, wire and dunnage.

    2. Lower loader to the ground.

    3. Install third-function oil lines and hoses, if ordered.

    4. Install loader-to-mid-mount couplers hydraulic hoses.

  3. Position loader on mounting frames.

  4. Install bucket/attachment carrier.

  5. Install bucket/attachment.

  6. Perform final inspection and adjustments.

  7. Install optional equipment/attachments.

OUMX005,0001E27-19-20060922