Recommended Set Up/Assembly Sequence
-
Prepare the tractor.
-
Refer to Prepare the Tractor section.
-
Install hood guard.
-
Install mounting frames.
-
Install multicoupler and hoses, if ordered.
-
Install toolbox support bracket and toolbox.
-
Install hydraulic valves and controls as needed.
-
Prepare the loader.
-
Remove all crates, parts and bucket/attachment from around loader
assembly.
-
Attach lifting straps to loader assembly and overhead hoist.
Lower loader assembly to ground (horizontal).
-
Remove and discard shipping banding, wire and wood pallet.
-
Cut paint mask rings off all cylinders.
-
Install locking pins.
-
Install timing rod.
-
Install third-function oil lines and hoses, if ordered.
-
Install loader-to-multicoupler hydraulic hoses, if ordered.
-
Install hydraulic control valve/hoses.
-
Install loader on tractor.
-
Install bucket/attachment.
-
Perform final inspection and adjustments.
-
Install optional equipment/attachments.
|
|