Testing of the Machine

Even when the machine is used properly, there will be some wear and tear, which may have major consequences at an advanced stage. In order to avoid this, the machine must be subjected to an (official)

maintenance test once every two years, and any defects must be repaired. Testing can take place at an officially recognized testing station, by an authorized tester.

WZ00085,00003F4 -19-20SEP05-1/2


A test pressure gauge connection (A) with 1 / 4 '' female thread is available on the boom center frame of the machine.

In order to measure the pump capacity, pressure line from the pump to the primary pressure regulator can be disengaged on the pump side by loosening the pump locking nut. A flow meter can then be attached to the nipple with 1 1 / 4 '' male thread.


A-Test pressure gauge connection

WZ290101869

WZ00085,00003F4 -19-20SEP05-2/2